Da Nang has given a stalled Hoi An beach resort a new financial footing. Under Decision 5079/QĐ-UBND, signed on 4 November, the city let Vinacapital Hoi An Tourism LLC (Công ty TNHH Khu du lịch Vinacapital Hội An) switch 51,789.2 m² of commercial and service land from annual rent to one-off rent. The one-off rent covers the rest of the 50-year term, which ends on 15 January 2057. The company is the developer of the project now marketed as Shantira Beach Resort & Spa. The decision was first reported by CafeF on 9 November.
Key facts
| Item | Detail |
|---|---|
| Project | Shantira Beach Resort & Spa, Hoi An (Da Nang city since the 2025 merger) |
| Developer | Vinacapital Hoi An Tourism LLC |
| Decision | 5079/QĐ-UBND, Da Nang People’s Committee, 4 November 2026 |
| Land affected | 51,789.2 m² of commercial and service land |
| Change | Annual rent to one-off rent for the remaining term |
| Term ends | 15 January 2057 (50 years from 15 January 2007) |
| Project size | 8.6 ha; three towers with 746 apartments and 70 beach villas |
| Charter capital | VND1,000 billion |
A 19-year project
The project began in December 2007 as Sofitel Hoi An, a US$16 million plan for 89 villas and 84 rooms. It stalled. In March 2018 Royal Capital, then called Hoang Gia Hoi An, bought the project company. Since then the plan has grown into towers, apartments and villas, and the deadline has been extended four times. The latest extension runs to December 2026.
Ownership changed again in July 2026. Phu Quoc Hoi An LLC now holds 90% of the project company and Royal Capital 10%. Phu Quoc Hoi An LLC is owned by Pham Thi Thu Ha (70%) and Pham Quang Vinh (30%), according to business registration data reported in the Vietnamese press. The general manager is Nguyen Phu Quy. The shares are pledged to VietinBank’s Hoi An branch.
Why one-off rent matters
Under annual rent, a developer pays the state every year and has limited rights over the land. Under one-off rent, the developer pays for the whole remaining term up front. In return, the 2024 Land Law allows the land-use right, and the buildings on it, to be mortgaged, sold or contributed as capital.
Our view: for a project with a December 2026 deadline and shares already pledged to a bank, that is the key point. One-off rent makes the land bankable. It gives the owners three options: borrow against the land to finish the build, bring in a partner, or sell the project with clean rights. All three are easier now than a week ago. Reports of the decision do not say how much the company must pay for the switch.
What we do not know
The reports say nothing about the construction deadline. We have not seen confirmation that the December 2026 date will be met or extended again. Nor do we know which hotel brand, if any, will run the finished resort, or how the apartments will be sold. The developer has not commented publicly.
Demand is another question. Our report on the low season in Hoi An shows how seasonal the market is, so timing matters for any buyer.
What it means for you
1. Investors in stalled projects
Look for projects that have switched to one-off rent. They are easier to buy, finance and exit than those still on annual rent.
2. Lenders
A one-off lease gives you collateral you can enforce. Check that the up-front rent has been paid in full before lending against it.
3. Operators
A project that can now raise money may soon look for a brand. Expect the owners to talk to operators if the build restarts.
4. Buyers of apartments or villas
Check the land status of each unit. Units on land with paid-up one-off rent are a safer purchase than units on annual rent.
FAQ
What did Da Nang decide about Shantira Hoi An?
On 4 November 2026 it let the developer switch 51,789.2 m² of land from annual rent to one-off rent until 15 January 2057.
Who owns the Shantira Hoi An project?
Phu Quoc Hoi An LLC holds 90% of the project company and Royal Capital 10%, since July 2026.
Why does one-off land rent matter?
Under the 2024 Land Law, land on one-off rent can be mortgaged, sold or used as capital. Land on annual rent has fewer rights.
When must the Shantira Hoi An project be finished?
Its current deadline is December 2026, after four extensions.
Was Shantira Hoi An once a Sofitel?
Yes. It began in 2007 as a planned Sofitel Hoi An with 89 villas and 84 rooms.